PROJECT DESCRIPTION
​
2005 AASHTO National Value Engineering Award: Most Value Added Proposal Preconstruction Engineering
​
The I-405 Storm Water project scope included storm water collection, conveyance, storage and treatment along 22 miles of I-405, the second largest North-South artery supporting Seattle, Redmond, Bellevue and Renton. MENG Analysis identified drainage system planning and construction alternatives that offered first cost or life cycle cost benefits and improved project quality.
​
MENG Analysis provided a total of 21 proposals yielding a total savings potential of $68,784,000. This savings represents 83% of the total project cost, with additional savings to be realized as proposals are applied to WSDOT's future projects.