top of page
project:
Lakewood High School
Lakewood School District
Location:
Arlington, Washington
Size:
160,922 SF
Estimated Cost:
$58 Million
Service:
Commissioning
Market Sector:
K-12 Education
Facility Specialty:
High School
PROJECT DESCRIPTION
​
MENG Analysis is providing WSEC and WSSP Fundamental and Enhanced Cx services including:
​
-
Project Preparation & Administration,
-
Commissioning Plan,
-
Document Review & Comment,
-
Pre-Startup Inspection,
-
System Start-up,
-
Test, Adjust & Balance (TAB) Verification,
-
Functional Performance Testing (FPT),
-
Training,
-
Cx Report, and
-
Post Occupancy.
Lakewood High School commissioned MEP systems include rooftop heat recovery AHUs, MAU, VAV TUs with electric reheat, exhaust fans, dust collector, DHW heaters, green house HVAC, sump pumps, ductless split A/C, boilers, building air barrier system, ceiling fans, DDC with occupancy and CO2 sensors, automatic lighting controls, electrical panels and sub-metering.